All changes to the APP are now captured in the Updated APP, which reflects both:
Revised entries, such as adjustments in
446 views
An Updated PPMP is required whenever revisions occur after the approval of the Final PPMP. These revisions may include:
Changes in cost
382 views
Yes. Under RA No. 12009 and its Implementing Rules and Regulations (IRR), the procurement rules apply to all procurement activities of government
490 views
For national government agencies, indicate the fund source reflected in the National Expenditure Program (NEP), since the Indicative APP is
354 views
Yes, but in a simplified way consistent with the principle of proportionality. Items that are mandatorily procured through PS-DBM (e.g.,
414 views
At least one Market Scoping Form per project requirement is needed. If the items are grouped into a single procurement
388 views
Section 2 is meant to reflect the initial or indicative budget allocation for the requirement. Section 4, on the other
108 views
Yes. Market Scoping is still required, but it does not need to be as extensive or detailed compared to other
401 views
Yes. Market Scoping applies to all procurement — big or small. Of course, for simpler items like meals or room
467 views